Lean pull production planning adoption in a major infrastructure construction project
Overview
An Australian Government Business Enterprise is delivering one of the nation's largest pumped hydro projects, creating critical clean-energy infrastructure and a major source of renewable generation.
Background
The project required a complex network of service and emergency access tunnels and a new underground transformer hall, delivered using drill-and-blast methodology. However, the scale and complexity of the works created significant schedule pressure, contributing to construction delays and cost escalation.
Action taken and solution
To support the client in replanning and controlling the revised drill-and-blast schedule, the Last Planner Methodology (a form of Lean Pull Production Planning) was introduced as a production control mechanism. This enabled crews to align daily execution with the revised blast plan while reducing the risk of further cost escalation. The approach was reinforced through integrated visual daily management boards that tracked drill-and-blast performance, highlighted deviations from plan, and identified containment actions and countermeasures for construction and related services teams to address in order to continue to meet planned blasts.
Results achieved and takeaways
- Daily shift-to-shift visual management gave teams clear visibility of completed work, incoming priorities, upcoming blasts, and constraints affecting current and future cycles.
- Defined actions and owners reduced the risk of unresolved issues carrying across shifts.
- A two-week look-ahead planning routine brought together all trades and services influencing the drill-and-blast cycle, improving coordination, schedule reliability, and confidence in achieving the replanned blast targets.